Delivered a critical PLC upgrade for a 210 MW power station, modernising aging and obsolete hardware to enhance reliability and performance.
Perform comprehensive upgrades to existing PLC software to suit new hardware ensuring mapping to SCADA remined intact.
Conduct rigorous functional and performance testing to validate system integrity and ensure compliance with operational standards.
Develop FAT and SAT completions report.
Perform commissioning, integrating upgraded systems into the existing control network.
Develop migration report (legacy to new system).
Perform risk assessment associated and documentation.
Rockwell ControlLogix PLCs
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behavior or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions. View our “Cookie Policy” and “Privacy Policy” for more information.