Project Overview

Tier16 delivered SCADA software development and implementation support for an integrated energy utility spanning generation, Battery Energy Storage Systems (BESS), and virtual power plants.

Tier16 engineers are embedded within Synergy’s engineering team, adding specialist Ignition SCADA capability and delivery capacity across thermal generation, BESS projects, and DER-based VPPs.​

Working within client-led project teams, they support SCADA design, development, integration, testing, commissioning, documentation and operator training.

Client Challenge

The client needed to strengthen internal Ignition SCADA capability across thermal generation, two BESS projects and DER-based VPPs. They also wanted to balance concurrent project delivery with ongoing BAU support; and​ leverage Tier Sixteen’s project-focused delivery methodology to expand project capacity without compromising BAU support.​

Tier16 Solution

Tier16 added dedicated project capacity while enabling the client’s engineers to maintain BAU support commitments​.

​The team helped to accelerate design, development, integration and commissioning across the project portfolio​ as well as supported testing, validation, documentation, training and AEMO and Western Power integration​.

Project Scope

/
Delivered comprehensive SCADA design and software development tailored to the client's specific operational requirements
/
Performed integration, testing, validation, and commissioning to ensure full functionality, reliability, and compliance with industry standards
/
Developed a comprehensive SCADA operator manual and delivered training to operators covering hands-on navigation, alarm management, and best practices
/
Integrated client systems with external market and network operator systems, including AEMO and Western Power

Technologies Used

/
Ignition SCADA

Project Outcomes & Impact

Embedded Tier16 engineers added dedicated Ignition SCADA capability, enabling multiple thermal generation, BESS and DER/VPP projects to progress concurrently.

Project-focused resourcing reduced pressure on the client’s engineering team, allowing them to maintain critical BAU support while advancing the project portfolio.​

Working within client-led teams transferred knowledge, embedded consistent delivery practices and developed reusable Ignition SCADA expertise for future projects.